Legal Advertisement DOCUMENT 00 11 13 - ADVERTISEMENT
Notices : Legals
http://djclassifieds.com/showads /ad/view/ad_id/17820464
Legal Advertisement
DOCUMENT 00 11 13 -
ADVERTISEMENT FOR
BIDS
Notice is hereby given
that sealed bids shall be
received, publicly opened
and read aloud.
For: CGHS Renova-
tions Package 3
By: Center Grove
Community School Corpo-
ration
At: Center Grove
Community School Corpo-
ration
Center Grove Educa-
tion Service Center
4800 W. Stones Cross-
ing Rd
Greenwood, IN 46143
Attn: Dr. Jason Taylor,
Associate Superintendent
AT: 11:00 a.m., local
time (EST), January 5,
2027
Bids received after
stated time shall be re-
turned, unopened.
Owner reserves the
right to accept or reject
any bid or waive any infor-
mality or error in bidding
for a period of 60 days
from bid opening date.
The Construction Man-
ager for this project will be
AECOM Hunt, 2450 South
Tibbs Avenue, Indianapo-
lis, IN 46241.
METHOD OF BIDDING
All work for the com-
plete construction of the
CGHS Renovations Pack-
age 3 will be bid under
separate prime contract
bids; they are as follows:
1. Bid Package #1 -
General Trades
2. Bid Package #2 -
Electrical
3. Bid Package #3 -
Stage Rigging
4. Bid Package #4 -
Audio/Visual
Bids shall be based on
a "stipulated sum" basis in
full accordance with Bidd-
ing Documents prepared
by CSO Architects, 8831
Keystone Crossing, Indi-
anapolis, IN 46240.
PREPARATION AND
SUBMISSION OF BIDS
Bids shall be executed
on State Form 96 and
Supplementary Proposal
Form included in the Proj-
ect Manual.
Bids shall be accom-
panied by AIA Document
A305 Contractor's Qualifi-
cation statement.
Bids shall be accompa-
nied by Contractor's Fi-
nancial Statement specific
enough and in such detail
so that the Owner can
make a proper determina-
tion of the Bidder's capa-
bility for completing the
project if awarded.
A Bid security in the
form of AIA Document
A310, a certified check, In-
diana General Revised
Form No. 86, "Contractors
Combination Bid Bond
and Bond for Construc-
tion" or a form from an ac-
ceptable surety shall ac-
company each bid. The
bid security shall be in the
penal amount of 5% of the
total bid price and made
payable to the Owner.
Bids shall be accompa-
nied by the Contract Re-
sponsibility Certification
(reference specification
section 00 21 00 Instruc-
tion to Bidders)
Should Bidder withdraw
his bid within 90 days from
bid opening date without
written consent of the
Owner or fail to execute a
satisfactory contract with
the Owner, the Owner
may declare the bid secu-
rity forfeited as liquidated
damages.
Prior to execution of the
Contract, Bidder shall fur-
nish Performance Bond
and Payment Bond in the
amount of 100% of the
Contract Sum. Bonds
shall remain in full force
and effect for 12 months
from date of acceptance of
the work.
BIDDING DOCU-
MENTS
Prime Bidders may ob-
tain Bidding Documents
from Eastern Engineering,
9901 Allisonville Road,
Fishers, IN 46038 by any
of the following methods:
1. Downloading a
complete set of Bidding
Documents. There is no
cost for downloading the
Bidding Documents.
2. Purchase printed
copies of bidding docu-
ments. Prime Bidders
shall obtain complete sets
of Bidding Documents.
This cost is
non-refundable.
Sub-bidders and suppli-
ers may purchase Bidding
Documents (download,
CD, printed) from Eastern
Engineering. This cost is
non-refundable.
Sub-bidders and suppliers
are responsible for deter-
mining the drawing sheet
numbers and spec division
numbers needed.
PRE BID CONFER-
ENCE
Contractors shall meet
with the Owner, Construc-
tion Manager and Archi-
tect at 03:00 p.m. on De-
cember 3, 2026, at the
Center Grove High School
Auditorium - located at
2717 S. Morgantown Rd
Greenwood, IN 46143 for
a Pre-Bid Conference and
Site Walk. - Meet at HS
Main Entrance
Any questions concern-
ing bidding the project
shall be directed to Brian
Vornheder
([email protected]) and Austin Gloyd
([email protected]).
TIME OF COMPLE-
TION
Bidders shall state com-
pletion time along with
their bid. Commence
Work within 48 hours after
signing contract or receiv-
ing a notice to proceed,
and complete Work ready
for completion as follows:
Start Date: June 1, 2027
Substantial Completion:
September 15, 2027
Final Completion:
October 30, 2027
OTHER PROVISIONS
The Center Grove
Community School Corpo-
ration does not discrimi-
nate on the basis of race,
color, religion, gender, na-
tional origin, age, or indi-
viduals with disabilities, in-
cluding limited English
proficiency, in its pro-
grams or employment poli-
cies as required by the In-
diana Civil Rights Act (I.C.
22-9.1), Title VI and VII
(Civil Rights Act of 1964),
the Equal Pay Act of 1973,
Title IX (Educational
Amendments), and Sec-
tion 504 (Rehabilitation
Act of 1973).
60165539
(J) 11-20-27-2026
Print this ad